Filed under EUDR Risk Assessment and Mitigation Explained
Plot record: legal status and review details
- Jurisdiction
- European Union
- Status
- Current consolidated Regulation (EU) 2023/1115, including the 2025 amendment and September 2026 consolidation. Main obligations are not yet generally applicable on the verification date.
- Application
- Generally 30 December 2026; 30 June 2027 for qualifying micro and small operators established by 31 December 2024 under Article 38(3), except products covered by the EUTR Annex; some newly added products apply from 30 December 2027. Check the product and actor-specific rules.
- Relevant provisions
- Articles 3, 4(5), 9, 10, 11 and 13
Review this page when:
- Amendments to Articles 9 to 13
- New Commission due diligence or certification guidance
- Changes in country benchmarking, supply routes or relevant adverse information
- Product-scope and application-date amendments
Change the exposure, then assess the replacement
Changing supplier or production area can address an EUDR concern when the new route removes the relevant exposure and is supported by adequate evidence. It is not enough to replace the name on an invoice. A new exporter may buy from the same plantations, collectors or mill that created the original concern, leaving the underlying risk unchanged.
Define why the existing route cannot support no or negligible risk. Is the problem an unresolvable origin gap, a credible land-rights claim, unreliable documents, uncontrolled mixing or known non-compliant production? That diagnosis determines what a replacement must change. Moving from one intermediary to another is ineffective if the decisive concern attaches to the production plot.
In the risk assessment and mitigation process, a replacement source receives its own information collection and assessment. Commercial urgency may justify dedicating more resources to that work, but cannot justify relying on an untested alternative. Keep the affected original goods blocked while assessing the proposed replacement.
Identify which parts of the route must differ
Compare the old and proposed chain at production, aggregation, processing and storage stages. Ask for stable identifiers and locations, not just trading names. Related companies can use different names for the same facility, and a broker may offer stock already held in the original warehouse. Establish whether the alternative is physically and evidentially distinct.
Where the concern is production-area specific, examine the new plots and relevant local conditions. A neighbouring plot may share a disputed boundary or land-use history. Where the concern is an intermediary's uncontrolled spot purchases, a direct route with demonstrable receiving controls may address it more effectively than changing to a distant producer while retaining that intermediary.
Assess transition arrangements too. Suppliers sometimes fulfil a new contract using old stock, subcontracted production or emergency purchases until their own harvest is available. Clarify which actual goods will fulfil the first orders and whether the new controls already operate. A plan for future production cannot establish the origin of current substitute stock.
Perform focused due diligence without copying approval
Collect the required Article 9 information for the new supply and assess the applicable Article 10 criteria. Reuse contextual research only where it remains relevant and current. A country overview may remain useful, while plot records, legal permissions, chain links and volume evidence need to match the new production and products.
Test the replacement against the specific failure that prompted the change. If the original supplier could not reconcile volumes, examine the new supplier's production capacity, purchases and stock records. If the problem involved falsified documents, consider independent verification and corroboration. A different supplier's promise to meet your policy is weak evidence that the original mechanism has been removed.
Low-risk country status can support Article 13 simplified due diligence only where its conditions are satisfied. Processing in a low-risk country does not change the production origin. A sourcing change should not be designed around a convenient export address while retaining standard-risk, high-risk or unknown-origin inputs behind it. Document how the actual origin and chain support the chosen approach.
A rubber sourcing change that initially fails
A rubber operator holds material because a processor cannot connect a portion of purchases to known farms. Purchasing proposes a new supplier that offers a fast shipment and a complete farm list. Initial review shows that the new supplier buys from the same processor and that the farm list describes its normal suppliers rather than the goods in stock.
The commercial counterparty has changed, but the original origin gap remains. The operator requests records connecting the offered shipment to the listed farms and examines whether an identifiable separate production stream exists. Without that link, the new farm list cannot establish the shipment's source. The operator keeps the proposed replacement on hold rather than treating the new vendor registration as a clean start.
A second option uses a different processor with a controlled receiving route and traceable production origins. The operator examines those records, relevant land-use and legal evidence, volumes and mixing controls. If the full assessment supports no or negligible risk, the source can be approved for the defined goods. The decision explains what changed and why the original concern does not carry across.
Manage consequences and avoid repeated re-entry
Record the status of the original supplier and affected stock separately from the approval of the alternative. A company may remain eligible for future engagement while a specific lot is rejected, or a recurring control failure may require a wider procurement block. The operational instruction should reflect the evidence and scope, rather than using a single permanent good-or-bad label for every transaction.
Make blocked origins visible across purchasing routes where appropriate, so that another broker does not reintroduce the same goods. Check aliases, shared facilities and subcontractors during onboarding. This is especially important when a supplier offers a substitute lot immediately after an adverse finding without explaining how its source differs.
Keep the original concern, options considered, replacement assessment and final rationale together. Article 11 requires documented mitigation decisions and at least annual review; meaningful new information requires earlier attention. Where products already placed or exported may be affected, a sourcing change does not remove relevant notification duties. Use the mitigation decision record to preserve both the operational change and the evidence supporting it.
Primary sources on the record
Articles 3, 4(5), 9, 10, 11 and 13. This entry was checked against the consolidated text dated 18 September 2026. Consolidated texts are documentation tools; the authentic acts are those published in the Official Journal.
- EUDR consolidated text, 18 September 2026
- Commission Guidance, July 2026
- European Commission guidance and implementation resources
Check the current sources and the guidance of the relevant competent authority for your situation. This page is not legal advice or a compliance determination.